07
2025
-
07
Core Considerations and a Comprehensive Management Guide for Transmission and Substation Construction Projects
Author:
The construction of transmission and transformation projects achieves high-quality, efficient, and environmentally friendly delivery through meticulous pre-planning, standardized process management, and innovative smart technologies. During the project, particular attention should be paid to the quality of foundation construction, safety in high-altitude operations, precision of equipment installation, and implementation of environmental protection measures. Moreover, it is essential to closely follow industry trends and actively adopt new technologies such as BIM, drones, and low-carbon materials to enhance the overall project effectiveness.
I. Pre-construction Preparation Phase
1.1 Design Review and Briefing
- Drawing Review Focus on verifying the line routing (e.g., compliance with regulations for crossing railways and highways), the overall layout of substation sites (equipment spacing ≥ 2 m), and the lightning protection and grounding system (grounding resistance ≤ 4 Ω).
- Geological exploration review Conduct on-site re-inspection of the foundation bearing capacity (e.g., for transmission tower foundations, the requirement is ≥150 kPa) and the distribution of underground pipelines to avoid design deviations.
- Technical standard alignment Confirm that the design complies with the “Construction and Acceptance Specifications for Overhead Transmission Lines from 110kV to 750kV” (GB 50233-2014) and the “Construction and Acceptance Specifications for High-Voltage Electrical Equipment in Electrical Installation Engineering” (GB 50147-2010).
1.2 Construction Organization Design
- Resource allocation :
- Personnel: The certification rate for special operation personnel (high-voltage electricians and work-at-height operators) is 100%, and each work team is fully equipped with safety supervisors.
- Equipment: Crane (rated load ≥ weight of tower materials + 10% safety margin), tensioner (tension control accuracy for cable laying ±5%).
- Construction Schedule Planning A three-level schedule is prepared using P6 software, with a 10% buffer time reserved for critical paths (e.g., foundation pouring → tower assembly → line stringing).
1.3 Materials and Equipment Management
- Acceptance of Materials Supplied by Party A :
- Conductor: Check the thickness of the galvanized layer (hot-dip galvanizing ≥85 μm) and tensile strength (steel-cored aluminum stranded wire ≥1270 MPa).
- Insulators: Mechanical Breakdown Load Test (porcelain insulators ≥ 50 kN); Power Frequency Withstand Voltage Test (no breakdown within 1 minute).
- Control of Supplier-Provided Materials :
- Concrete: Mix Design (C25 concrete, water-cement ratio ≤ 0.55; slump: 180 ± 20 mm).
- Reinforcing bars: Mechanical property testing (yield strength ≥ 335 MPa); weld joint inspection (100% pass rate in ultrasonic testing).
II. Key Control Points in the Construction Process
2.1 Foundation Construction
- Earth excavation :
- Excavation dimension deviation (length/width/height ≤ ±50mm); slope control (slope coefficient: 1:0.5 to 1:1).
- Puddle pits shall be provided (with a depth ≥ 0.5 m), and a backup drainage pump shall be installed to prevent the trench from becoming flooded.
- Formwork Engineering :
- Template stiffness verification (deflection ≤ 1/400 of the span); joint sealing (leak-proof grouting measures).
- Pre-embedded component positioning (center deviation of anchor bolts ≤ 2 mm, elevation deviation ≤ 5 mm).
- Concrete pouring :
- Layered vibration (each layer thickness ≤ 300 mm, vibration time 15–30 s).
- Maintenance covering (plastic film + straw bags; maintenance period ≥ 14 days).
2.2 Tower Assembly
- Ground assembly :
- The bolts are threaded in a uniform manner (vertically from bottom to top, and horizontally from inside to outside).
- Tower material bending control (main members ≤ 1/1000, secondary members ≤ 1/750).
- Overall tower erection :
- Pole selection (lattice-type poles shall have a permissible load ≥ 1.2 times the tower weight, accounting for a safety factor).
- Verticality adjustment (tower tilt rate ≤ 0.3%).
- Bolt tightening :
- Torque re-inspection (torque for M24 bolts ≥ 250 N·m, with a sampling rate ≥ 10%).
2.3 Overhead Line Construction
- Conductor and ground wire stringing :
- Tension control (conductor tension ≤ 25% RTS, ground wire tension ≤ 20% RTS).
- Crossing construction (erecting protective sheds over highways and railways; using insulated cable bridges for energized lines).
- Attachment installation :
- Metal fittings connected (bolts aligned in the same direction, split pins doubled and bent).
- Jumper wire fabrication (sag deviation ≤ ±2%, equipotential wires securely tied).
- Parameter measurement :
- Conductor-to-ground clearance (for 500kV lines ≥ 8.5 m, measured at crossing and overpass points).
- Sag observation (parallelogram method, error ≤ ±2%).
2.4 Substation Equipment Installation
- Main transformer installation :
- Body inspection (core insulation resistance ≥ 1000 MΩ, winding DC resistance difference ≤ 2%).
- Oil filling and nitrogen purging (vacuum level ≤133 Pa, holding time ≥8 hours).
- GIS installation :
- Cleanliness control (particle count ≤ ISO 4406 Class 18/16).
- Flange connection (bolt tightening torque complies with the manufacturer’s requirements; sealing groove is clean and free of scratches).
- Secondary wiring :
- Cable laying (bending radius ≥ 10 times the cable’s outer diameter; reliable grounding of the shielding layer).
- Circuit verification (insulation resistance ≥ 10 MΩ, withstand voltage test: 2 kV/1 min).
III. Special Measures for Safety and Environmental Protection
3.1 Safety Management
- Hazard Identification :
- High-altitude fall (tower assembly/line stringing operations, with dual-hook safety belt and fall-arrest device installed).
- Electric shock risk (when working near energized equipment, maintain a safe distance: 10 kV ≥ 1.0 m, 500 kV ≥ 6.0 m).
- Lifting injuries (the “Ten No-Lift” rules for lifting operations, with clear command signals).
- Emergency Management :
- Emergency plan preparation (specialized plans for electric shock, fire, and collapse).
- Emergency supplies reserve (fire extinguishers, first-aid kits, stretchers—checked monthly).
3.2 Environmental Management
- Pollution Prevention and Control :
- Noise control: Pile-driving operations shall be conducted between 6:00 and 22:00, with noise levels not exceeding 70 dB.
- Dust control (enclosure of concrete mixing stations, with water spraying for dust suppression at a frequency of ≥2 times/hour).
- Resource Circulation :
- Recycling of scrap steel (recycling rate ≥95%, stored separately by type).
- Construction wastewater treatment (settling ponds installed; discharge after pH adjustment to 6–9).
- Ecological conservation :
- Vegetation restoration (temporary land reclamation, planting native species).
- Animal passage installation (routing paths avoid protected areas, and animal bridges are constructed at crossing points).
IV. Integration of Acceptance and Operations & Maintenance
4.1 Acceptance of Concealed Works
- Basic acceptance :
- Reinforcement work (deviation in cover thickness ≤ ±5 mm, deviation in rebar spacing ≤ ±10 mm).
- Concrete strength (tested by rebound method; the strength of test cubes cured under the same conditions ≥ 90% of the design value).
- Grounding acceptance :
- Grounding electrode burial depth (≥0.8 m; if soil resistivity is high, replace with a resistance-reducing agent).
- Contact voltage test (contact potential ≤ 50V, step voltage ≤ 10V).
4.2 System Debugging
- Unit debugging :
- Transformer partial discharge test (≤100 pC, 500 kV equipment).
- Circuit breaker closing and opening characteristics (synchronism ≤ 5 ms; speed conforms to the manufacturer’s curve).
- Joint commissioning test :
- Protection setting verification (differential protection ratio restraint coefficient: 0.3–0.5; operating time ≤ 30 ms).
- Integrated commissioning of the automation system (remote control accuracy: 100%; telemetry accuracy ≤ 1%).
4.3 Operations and Maintenance Handover
- Document handover :
- As-built drawings (electronic version + paper version, with clear markings for any changes).
- Equipment manual (operating procedures, maintenance schedule, list of wear parts).
- Training Services :
- Practical Training for Operations and Maintenance Personnel (Key Points for Equipment Inspection, Abnormality Handling Procedures).
- Digital platform integration (data connection with online monitoring systems, threshold alert settings).
V. Application of Innovative Technologies
5.1 Intelligent Construction
- BIM application :
- 3D modeling (route optimization and collision detection to reduce design changes).
- Construction simulation (tower assembly process animation, early identification of operational risks).
- Drone Inspection :
- Line re-survey (aerial survey-generated DEM, accuracy ≤ 0.1 m).
- Construction monitoring (real-time video transmission, AI-based identification of quality hazards).
5.2 Green Building Materials
- Low-carbon concrete :
- Fly ash content ≥ 30%, carbon emission reduction benefit ≥ 20%.
- Use of recycled aggregates (crushed stone replacement rate ≥50%, strength grade ≥C25).
- Environmentally friendly insulating material :
- Plant-oil transformer (biodegradable, flash point ≥300℃).
- Composite insulator (silicone rubber sheds, with a 30% improvement in pollution flashover resistance).
VI. Summary
Transmission and transformation project construction approved. Refined preliminary planning, standardized process control, and intelligent technological innovation. To achieve high-quality, efficient, and environmentally friendly project delivery, the following aspects require particular attention during the process: Quality of foundation construction, safety of high-altitude operations, accuracy of equipment installation, and implementation of environmental protection measures. And closely follow industry trends by actively adopting new technologies such as BIM, drones, and low-carbon materials to enhance the overall efficiency of projects.
Exploring the Mysteries and Challenges of Transmission and Substation Engineering Construction
Gain an in-depth understanding of the knowledge related to transmission and transformation engineering construction, and master industry trends and key technical points.
2025-12-11
What does electrical engineering include?
Thermal Power Engineering: Electricity generation through the combustion of fossil fuels (such as coal and natural gas), including construction of the main plant building, boiler installation, and environmental protection projects.
2025-12-10